Data center · Decommissioning and exit

Data center decommissioning: checklist, timeline and how to choose a provider

Data center decommissioning is the planned shutdown of a server room, colocation cage or whole data center: confirm every workload has moved, power down, sanitize or destroy every data-bearing device, de-install and remove the equipment under chain of custody, resell or recycle it, remove whatever infrastructure your lease requires, and hand the space back with a record for every asset.14 Plan backward from the lease or contract end date; one colocation advisor recommends starting 9 to 12 months ahead, because most of that time goes to migration, not to pulling hardware.1 UPS batteries, refrigerants and halon carry their own federal rules.131517 Below: the phases, a printable checklist, a timeline planner, cost drivers, colocation exit terms and an RFP checklist. We're a buyer's guide and referral service, not a decommissioning provider.

Updated · How we research

What data center decommissioning includes

A decommissioning project has three layers, and quotes often cover only the first: the IT equipment, the workloads and data on it, and the facility around it. ITAMG, an ITAD provider, splits the work the same way: workload migration, IT equipment decommissioning, and facility decommissioning, which it says should be specified separately from the IT work.4 A partial job, such as retiring a row of servers in a live room, uses the same steps at smaller scale; Uptime Institute says underutilized and comatose servers typically make up 20 to 30% of a company's server install base, so discovery alone often finds hardware nobody needs.10

Decommissioning workstreams, what each covers and who usually does it. Sources: ITAMG, Iron Mountain, Park Place Technologies and DC Decom service descriptions; EPA and OSHA for regulated work.
WorkstreamWhat it coversUsually done by
Inventory and asset auditEvery rack, device, drive, cable, UPS and battery string, with serial numbers, owner, location and the planned outcome for each.47Your IT team, often with the provider's discovery tools
Migration and dependenciesMoving or archiving each workload, then signed acceptance before anything is switched off.84IT and application owners
Change freeze and power-downApproved shutdown windows, ordered shutdown of software and hardware, then electrical isolation by qualified people.7818IT, facilities, electricians
De-racking and de-cablingRemoving servers, storage, network gear, rails, PDUs and IT cabling from racks.57Decommissioning or ITAD provider
Data sanitizationErasure or destruction of every drive and data-bearing device, on site or at the provider's plant, with device-level records.4Provider, to the method you approve
Packing and logisticsProtective packing, sealed containers, manifests, transport and a receiving count that matches what left.4Provider
Resale, redeployment and recyclingRouting each asset to reuse, resale, return to its lessor or certified recycling, with a settlement report.47Provider; you approve routes
Infrastructure removalUPS systems and batteries, CRAC/CRAH units, raised floor, cable trays and abandoned cable, as your lease or plans require.49Provider and licensed trades
Lease restoration and handbackReturning the space to the condition the lease or colocation contract requires, then a walk-through and sign-off.91You, landlord or colocation provider
Final reportingAsset reconciliation, sanitization and destruction certificates, recycling records, and updates to finance for write-offs and cancelled maintenance contracts.74Provider delivers; you reconcile

Decommissioning is not the same as relocation. Relocation moves equipment to a new site and keeps it running; decommissioning shuts the old site down, and most exits do some of each.1 For a general explanation of IT asset disposition, see the ITAD services overview.

The phases of a decommissioning project, in order

Run the project in seven phases, each closed by a sign-off before the next starts. The order matters most at two gates: nothing is powered down until the workload owner signs a go/no-go, and nothing leaves the building until it is on the approved asset list.84

Seven phases of data center decommissioning A vertical sequence of seven numbered phases. 1 Discover: inventory and dependency map. 2 Select a provider: RFP and site walk. 3 Migrate: move workloads, go/no-go sign-off. 4 Power down: change freeze and electrical isolation. 5 Remove: sanitize, de-rack, pack, ship under custody. 6 Restore: infrastructure removal if the lease requires it. 7 Close out: handback, reconciliation and certificates. Two gates are marked: a go/no-go gate between phases 3 and 4, and an approved-asset-list gate between phases 4 and 5. 1Discover 2Select a provider 3Migrate 4Power down 5Remove 6Restore 7Close out Inventory, serials, dependency map RFP, site walk, award Move workloads in waves Change freeze, isolate circuits Sanitize, de-rack, pack, ship Infrastructure, if lease requires Handback, reconcile, certificates Gate: go/no-go signed Gate: approved asset list
Phase grouping is our synthesis of published process guides; the go/no-go and release gates follow Modern Waste Solutions and ITAMG.847
  1. Discover. Build the baseline inventory and dependency map: applications, databases, storage, backups, network routes, authentication, monitoring and external connections. Record leased and third-party-owned equipment, and every contract with a notice date.871
  2. Select a provider. Issue the RFP with the inventory attached, hold a site walk so bidders see access, loading docks and floor limits, and award with a written scope and change process.48
  3. Migrate. Move workloads in waves with both sites live until each wave is accepted; verify backups and test restores first.18
  4. Power down. Freeze changes, shut down in an agreed order, then have qualified electrical staff isolate and lock out circuits. IT shutdown and electrical de-energization are different steps with different owners.818
  5. Remove. Sanitize or destroy media, de-rack, pack, seal and ship, recording each custody handover. Reconcile what was approved, what was removed and what was received.4
  6. Restore. Remove infrastructure the lease or your plans require, from cabling to UPS and cooling units, using licensed trades for electrical and refrigerant work.49
  7. Close out. Walk the space with the landlord or colocation provider, return badges and keys, file certificates, and give finance the write-offs, resale proceeds and cancelled support contracts.71

Data center decommissioning checklist

Use this as a working checklist; each line should end up with an owner, a date and evidence. It prints cleanly from your browser. It's compiled from the process guides and federal rules cited on this page.8471

Before you start

  • Name one accountable project owner and define the scope: which rooms, cages, racks, circuits and contracts are in, and which are out.8
  • List every notice date: lease, colocation contract, carrier circuits, maintenance and software support.17
  • Confirm in writing what the lease or colocation contract requires you to remove or restore, and who owns racks, PDUs, UPS, cooling and raised floor.43
  • Set the budget with service costs and expected resale credit as separate lines.4

Inventory and asset audit

  • Scan every device by serial number and asset tag; reconcile against your asset management records.74
  • List every data-bearing item separately: drives in servers and arrays, loose drives, SSDs, backup tapes and storage embedded in network or management gear.4
  • Flag leased and third-party equipment, with the lessor's return and data-handling instructions.4
  • Assign each asset an outcome: redeploy, resell, return, destroy or recycle.4
  • Inventory UPS battery strings (chemistry, count, condition), cooling units holding refrigerant, and any halon fire suppression.8141517

Migration and go/no-go

  • Map dependencies, including DNS, firewall rules, authentication, certificates, monitoring and remote management.8
  • Verify backups and test restores for systems being retired or moved.8
  • Get workload owners' written acceptance for each migration wave.8
  • Hold a formal go/no-go with named authority to stop, and let technicians stop work if they find live links or unknown drives.8

Power-down and de-installation

  • Approve the change freeze and shutdown sequence.87
  • Have qualified electrical staff de-energize and lock out or tag the circuits before anyone works on or near them.18
  • Release each rack for removal only against the approved asset list; keep retained equipment marked.4
  • Segregate batteries and keep damaged lithium batteries apart from intact ones.814

Data sanitization and logistics

  • Approve the sanitization method and location (on site or off site) for each media type, plus how failed or unreadable drives are handled.4
  • Record device-level results and resolve every exception before final payment.4
  • Seal containers, list contents on manifests, and record releasing and receiving parties at every handover.4
  • Match the receiving count at the provider's facility to what left your site.4

Infrastructure, restoration and handback

  • Have refrigerant recovered by EPA-certified technicians before cooling equipment is dismantled or scrapped.1516
  • Send halon-containing equipment only to a facility that recovers halon to NFPA 10 and 12A.17
  • Route UPS batteries through universal waste (or, for lead-acid, 40 CFR 266 subpart G) and the required DOT packaging.1314
  • Remove the accessible portion of abandoned cable, or tag cable you're keeping for future use.19
  • Complete restoration, the final walk-through and sign-off, and return keys, badges and access cards.91

Closeout

  • Get the final asset reconciliation: approved, removed, received and final outcome, with an exception list.84
  • File certificates of sanitization or destruction and recycling records for audit.14
  • Update the asset register; give finance resale proceeds and write-offs; cancel maintenance contracts and licenses.71
  • Cancel circuits and cross-connects, and confirm the date billing stops.12

Who does what: your team, the provider, facilities, the colo and trades

You own the decisions; the provider does the physical IT work; facilities, the landlord or colocation provider and licensed trades handle the building. Write that split into the statement of work, because disputes usually start where it's vague.84

Typical responsibility split on a decommissioning project. Sources: Modern Waste Solutions client/vendor table, ITAMG scope guidance, EPA and OSHA rules for regulated work. Your contracts may divide it differently.
TaskOwnerSupports
Scope, asset list, disposition instructionsYour IT teamProvider scans, reconciles and reports differences8
Migration, go/no-go, shutdown approvalIT and application ownersProvider follows the authorized scope8
Electrical isolation (PDUs, panels, UPS)Facilities with qualified electrical staffProvider verifies the boundary before handling818
De-rack, de-cable, pack, transportDecommissioning or ITAD providerYou approve routes, access and work hours84
Data sanitization or destructionProviderYou approve the method and any witnessing84
Resale, recycling, settlementProviderYou approve outcomes and check deductions4
UPS batteriesProvider or battery contractor with a universal waste routeYou supply system history and condition813
Refrigerant recovery from cooling unitsEPA Section 608 certified technicianHVAC contractor or provider subcontract16
Halon or other fire suppressionFire protection contractorRecovery facility operating to NFPA 10 and 12A17
Heavy equipment movesRiggersFacilities confirms floor loading, routes and docks8
Raised floor, trays, abandoned cable, restorationProvider, cable abatement or general contractorLandlord or colo accepts the space94
Notices, cross-connects, final walkYouColocation provider or landlord21
Asset register, write-offs, contract cancellationsIT asset management and financeProvider's final reports7

How long decommissioning takes, and a planner

Most of a decommissioning timeline is migration and lead time, not hardware removal. Metro Colo Advisory, a colocation advisor, suggests 9 to 12 months from first inventory to handback for a typical enterprise data center, with the physical shutdown often only the last month or two.1 Removal itself can be fast with enough crews: Iron Mountain reports a hyperscale project of 297 racks and 121,893 drives where all racks were data-free four days after the start and all assets were off site within 14 days.5 What usually sets your dates:

  • Notice windows. Equinix asks for a termination date 90 to 365 days after the request; Metro Colo Advisory says retail colocation non-renewal windows of 60 to 90 days are common and 6 to 12 months is common at wholesale.21
  • Migration. The number of applications, their dependencies and how many waves the business will accept.81
  • Access. Escorts, restricted work windows, loading dock and elevator bookings and floor limits slow crews down.48
  • Data treatment. On-site sanitization or shredding needs space, power, setup and throughput; off-site needs secure staging and transport.4
  • Infrastructure and restoration. Electrical, refrigerant and structural work need their own specialists and permissions.4

Enter your rack count, exit date and scope. The planner lays out a backward schedule and tells you when discovery must start. Worked example (the defaults): 20 racks in an owned or leased room, a 16-week migration, on-site drive treatment, racks and cable removed, a 4-week buffer and a 90-day notice period need about 32 weeks. Discovery starts 32 weeks before exit, power-down is 12 weeks before, de-installation runs from 11 to 8 weeks before, and notice goes out about 13 weeks before.

Decommissioning timeline planner

Planner

Plan length

32 weeks

Start discovery by

32 weeks before exit

Send notice by

About 13 weeks before exit

Enter your exit date to see calendar dates and whether you have enough time.

Backward schedule for the inputs above: each phase in weeks before the exit date, calendar dates once an exit date is entered, and who usually leads
PhaseWeeks before exitDatesLed by
Discovery: inventory, serial numbers, dependency map, contracts32 weeks before to 28 weeks before–Your IT team (provider can help)
Provider selection: RFP, site walk, award28 weeks before to 22 weeks before–IT, procurement, security
Migration in waves, then go/no-go sign-off28 weeks before to 12 weeks before–IT and application owners
Change freeze, power-down, electrical isolation12 weeks before to 11 weeks before–IT, facilities, qualified electricians
De-install, on-site sanitization or destruction, pack, remove under custody11 weeks before to 8 weeks before–Decommissioning/ITAD provider
Racks, cable trays and abandoned cable removal8 weeks before to 6 weeks before–Provider and licensed trades
Buffer for slips and punch-list items6 weeks before to 2 weeks before–Project manager
Restoration sign-off and handback to landlord or facilities2 weeks before to exit date–You, facilities, landlord
Final reconciliation, certificates, settlement report8 weeks before to 6 weeks before–Provider delivers; you reconcile

How it works: the planner counts backward from your exit date. Durations are our editorial planning assumptions, not industry standards, and are meant to be replaced by your provider's schedule once you have one: discovery 3 weeks plus 1 week per 25 racks; provider selection 6 weeks, run in parallel with migration, with at least 4 weeks between award and power-down for the site survey and crew booking; your migration window; 1 week for change freeze, power-down and electrical isolation; de-install, packing and removal 1 week plus 1 week per 40 racks, plus 1 week when drives are treated on site; infrastructure removal 1 week plus 1 per 50 racks (racks, trays and cable only) or 3 weeks plus 1 per 25 racks (full removal); your buffer; and handback 2 weeks (own or leased facility) or 1 week (colocation). Partial weeks round up. Final reports are assumed 2 weeks after removal for on-site treatment and 4 weeks for off-site, and can land after the exit date. It doesn't account for permits, utility work, holidays or restricted work windows.

What decommissioning costs, and how resale offsets it

Price a decommissioning project as a net figure: the service cost minus the resale credit you actually receive. ITAMG puts it as net project cost equals agreed service and project costs minus net recovery credited to you, and notes that a negative result is estimated proceeds, not a promised payout.4 There is no published industry price index; the only per-project ranges we found come from individual providers.

What changes the price of a decommissioning project, and what to pin down in the quote. Source: ITAMG cost-driver table, paraphrased.
Cost driverWhy it moves the priceWhat to clarify
Labor and accessDense racks, heavy equipment, escorts and restricted windows add labor.Shifts, mobilization, minimum charges, waiting time, extra visits
Data treatmentMedia type, volume, method and location change throughput.Per-device charges, on-site setup, witnessing, failed-media handling
Packing and transportDestination, protection and site constraints drive logistics.Packaging, crating, freight, insurance, storage
Facility workCable removal, specialist disconnections and restoration go beyond collection.Exact handback condition, contractor boundaries, permits, disposal streams
Processing and reportingTesting, sorting, reconciliation and evidence take work after pickup.Included reports, delivery dates, recycling charges
Recovery creditModel, configuration, condition, ownership and demand set resale value.Firm offer or estimate; deductions, settlement timing, unsold items

Source: ITAMG.4

One provider publishes ranges. Treat them as that company's estimates for its own market, not a quote or a national benchmark:

Estimated decommissioning cost and value recovery by project size, Phoenix, Arizona, 2026, as published by Phoenix ITAD from its own project history. US dollars. Not independently verified.
Project sizeAsset countEstimated costValue recovery potential
Small server room1 to 10 racks, under 100 assets$2,500 to $8,000$3,000 to $15,000
Mid-size data center10 to 50 racks, 100 to 500 assets$8,000 to $35,000$15,000 to $75,000
Large enterprise data center50 to 200 racks, 500 to 2,000 assets$35,000 to $150,000$50,000 to $300,000
Hyperscale or multi-site200+ racks, 2,000+ assetsCustom pricing$200,000+

Source: Phoenix ITAD, updated June 2026.6 The company says actual costs depend on project requirements. Recovery depends heavily on equipment age and configuration; older or end-of-support hardware may recover little.

At the large end, Iron Mountain reports $4.4 million in client proceeds from remarketing the equipment in its 297-rack hyperscale case.5 Three cautions apply to any offset:

  • Know what kind of credit you're getting. A firm purchase offer, a forecast and a share of future sale proceeds commit the provider to very different things. Ask about deductions, payment timing and who bears unsold equipment.4
  • Don't destroy value by default. Get a resale assessment before approving treatment that removes the resale option, such as shredding drives in equipment that could be resold after verified erasure.4
  • Infrastructure work is usually extra. Restoration, cable abatement and UPS or cooling removal are often quoted separately from the IT scope.49

The biggest exit costs often sit outside the decommissioning quote: overlapping rent while both sites run, migration labor and the new environment.1 For how buyback offers for servers, storage and network gear are built, see server recycling and buyback.

Data sanitization during decommissioning: on site or off site

Decide the method and the location for each media type before any device is released, and get device-level records back. Treat on site when your policy says media can't leave unsanitized or you need witnessing; treat off site when policy allows controlled transport, with custody controls for unsanitized media in transit.4

  • Use the current NIST guidance. NIST published SP 800-88 Revision 2 on September 26, 2025. It shifts the focus to running an enterprise media sanitization program and, apart from cryptographic erase, replaces technique details with a recommendation to follow IEEE 2883, NSA specifications or an organizationally approved standard.11
  • Find all the media. Formatting a volume or deleting a virtual machine doesn't sanitize the drive under it; include loose drives, tapes and storage embedded in network and management equipment.4
  • Check agency-specific rules. For example, the IRS requires that destruction of media holding federal tax information be witnessed by an agency employee, with limited exemptions written into the contract.12

Choosing between erasure, purge and destruction, and what a valid certificate must show, is covered in certified data destruction and NIST 800-88 methods. For shred trucks, particle sizes and per-drive pricing, see hard drive shredding services.

Batteries, refrigerants, halon and electrical safety

Facility equipment brings federal environmental and safety rules that IT equipment doesn't, and states can be stricter. Confirm the provider or its named subcontractor handles each one.14

Regulated items commonly found in a data center exit, the federal rule and what to require. Sources: EPA and OSHA pages cited in each row, checked November 27, 2026.
ItemFederal rule (summary)What to require
Lithium-ion UPS batteriesEPA says most lithium batteries are likely hazardous waste at disposal (ignitable and reactive) and recommends businesses manage them under the universal waste rules, 40 CFR part 273. Damaged batteries can't go by air and need DOT packaging under 49 CFR 173.185(f).14A named recycler, segregation of damaged units, trained handlers, DOT-compliant packing
Lead-acid (VRLA or flooded) UPS batteriesSpent lead-acid batteries can be managed under 40 CFR part 266, subpart G, or under the universal waste rules.13Which rule the provider uses, the destination recycler, shipping records
Universal waste limitsSmall quantity handlers accumulate under 5,000 kg; large quantity handlers 5,000 kg or more. Universal waste can generally be stored for a year and shipped without a hazardous waste manifest.13Weigh the battery plant against the 5,000 kg threshold; set a removal date
Refrigerant in cooling equipmentEquipment typically dismantled on site, such as chillers, must have refrigerant recovered under EPA's servicing rules before disposal. Technicians who dispose of equipment that could release refrigerant must be Section 608 certified.1516The technician's certification type, recovery records, where the refrigerant goes
Halon fire suppressionHalon-containing equipment may be disposed of only by sending it for halon recovery to a facility operating to NFPA 10 and 12A; halon itself only goes to recycling or approved destruction.17The fire protection contractor and recovery facility
Electrical workOSHA requires live parts be de-energized before employees work on or near them (with narrow exceptions) and the circuits locked out, tagged or both.18A site safety plan naming who isolates and verifies each circuit
Abandoned cableThe NEC requires removal of the accessible portion of abandoned communications and Class 2/3 cable unless it's tagged for future use.19A cable scope that matches your code edition and your lease

State e-waste laws, landfill bans and downstream recycler certification are covered in the IT equipment recycling guide.

The risks that cause most decommissioning problems

Most failures are record-keeping failures, not equipment failures: a missed dependency, a drive nobody listed, a serial number that doesn't reconcile, or a contract that renewed because notice went out late.814

Common decommissioning risks, how they show up and the control that prevents each. Sources as cited per row.
RiskWhat it looks likeControl
Live dependency switched offProduction traffic, a shared key or an authentication service still on old hardware.8Dependency map, traffic validation and a signed go/no-go
Missed or extra assetsDevices on the floor that aren't on the list, or the reverse.74Serial-level baseline; removal only against the approved list
Lost serials in transitA shipment arrives but a device can't be matched. GPS shows where a truck went, not whether a device arrived.4Sealed containers, manifests, receiving reconciliation
Data exposureLoose drives, tapes or embedded storage outside the sanitization scope; failed drives with no exception route.4Separate media inventory; device-level results; resolved exceptions
Selling what you don't ownLeased or third-party equipment sent for resale.4Ownership flagged in the inventory; lessor instructions followed
Contract renews or charges continueA missed non-renewal window, or circuits and support contracts left running.17Notice calendar; cancellation list with dates billing stops
Battery fire or releaseDamaged lithium cells mixed with intact ones or stored near combustibles.14Segregation, inspections, trained handlers, EPA storage practices
Refrigerant or halon ventedCooling or suppression equipment scrapped without recovery.1517Certified technicians; recovery records before removal
Electrical injuryIT shutdown mistaken for electrical isolation.818Lockout/tagout by qualified staff; verified boundaries

Leaving a colocation cage: what's different

In colocation, the contract sets the clock: you give notice, remove everything by the end date and leave the space as the contract requires. The building, power and cooling usually stay with the provider, so infrastructure removal is rarely yours, but cabinets, cabling and cage contents may be.14

  • Notice. Equinix's process asks for a preferred termination date 90 to 365 days after the request; billing ends on the termination date, and for full account or deployment terminations a customer project manager assists with decommissioning.2 Retail and wholesale windows vary; Metro Colo Advisory says a missed window can renew the contract for another full term.1
  • Removal deadline. In one published Equinix agreement, the customer must remove all equipment on or before expiry. After 10 days Equinix may remove and return it at the customer's risk and invoice the cost, may treat unclaimed equipment as abandoned, and after 30 days' written notice may liquidate it and keep the proceeds.3 Equipment that leaves your control that way could still hold drives, so finish sanitization well before the deadline.
  • Circuits and cross-connects. Cancel carrier circuits and interconnections separately and confirm the date each stops billing.14
  • Site rules. Book loading docks, escorts and work windows with the colocation provider, and get its handback requirements in writing before you scope the job.48

How to choose a data center decommissioning provider

Choose on proof of process for your kind of site: serial-level reconciliation, a sanitization method you've approved, a named route for every regulated item and a clear commercial model. Certifications matter, but check them in the certifier's own registry and confirm which facility and activities they cover.4 For an unranked list of national providers and how to verify their certifications, see the ITAD companies directory.

RFP checklist for decommissioning services

  • Scope by workstream. IT de-install, data treatment, logistics, resale and recycling, infrastructure removal and restoration priced as separate lines, with exclusions listed.4
  • Certifications. Which R2v3, e-Stewards or NAID AAA certificates apply, to which facilities, and the registry link for each.
  • Sanitization. Method by media type and the standard it follows (NIST SP 800-88 Rev. 2, IEEE 2883), on-site capacity and daily throughput, and how failed drives are handled.114
  • Chain of custody. Seals, manifests, custody signatures and a sample reconciliation report showing approved, removed, received and final outcome.48
  • Commercial model. Fixed price, time and materials, or recovery share; for any credit, whether it's a firm offer, the deductions, settlement timing and unsold-equipment terms.4
  • Regulated items. Battery recycler and handling rule, refrigerant technicians' Section 608 certification, halon recovery facility.131617
  • Safety. A site-specific safety plan, who performs electrical isolation, and how lockout boundaries are verified.188
  • Subcontractors. Every subcontractor named, with the work each does.
  • Insurance. Certificates for the coverage types and limits your risk team requires.
  • Schedule. Crew size, shifts, mobilization date and the date each report is delivered.4
  • Downstream. Where equipment and materials go after the provider's plant, and how that is documented.4
  • References. Two recent projects of similar size and type (owned room, colocation exit or full facility).

Limits of this guide

This page summarizes published sources as they read on November 27, 2026. It isn't legal, environmental or engineering advice. Federal rules are summarized; states can be stricter, and the NEC edition in force depends on your jurisdiction. Contract terms quoted come from one provider's published documents; your own lease or colocation agreement governs. Cost figures are one vendor's estimates for one market and aren't a quote. The planner's durations are our editorial assumptions, not industry standards. We haven't verified any company's claims, and citing a company isn't an endorsement.

What to send for a decommissioning quote

A provider can scope the job and plan a site walk faster with these details:

  • Site address, and whether it's your own facility, a leased building or a colocation cage.
  • Rack count, rough device counts by type, and the number of drives if known.
  • Exit date and any notice date already set.
  • Where drives must be treated (on site or off site), and any witnessing or regulatory requirement.
  • Infrastructure in scope: none, racks and cabling, or UPS, batteries, cooling and raised floor too.
  • Leased or third-party equipment, and what you hope to resell or redeploy.
  • Access limits: work hours, escorts, loading dock, elevator and floor-loading constraints.

The planner's "Add this schedule to my quote request" button copies your inputs and dates into the form.

Request decommissioning quotes through IT Asset Disposal Services

Send one request with your project details. A person reviews it and, where we can identify providers that fit the site and scope, shares it with up to two of them. We don't yet have agreements with any providers, so we can't promise how many will respond or how quickly. Any provider that does contacts you directly, and you decide whether to hire anyone. It's free for buyers. Providers who receive requests may pay us a referral commission; the referral disclosure explains how. We don't de-install, sanitize, transport, recycle or buy equipment, and routing a request isn't an endorsement. Read how requests are handled, or go to the request form.

Request decommissioning quotes

Sources

  1. Data Center Decommissioning: The Process, Checklist and Timeline, Metro Colo Advisory, Updated November 22, 2026. Colocation advisory firm that says providers pay it for placements. Cited for its planning-lead and notice-window guidance, which it describes as typical terms. Checked 2026-11-27.
  2. Termination Requests, Equinix Product Documentation. How Equinix customers request a full account, deployment or product termination. Checked 2026-11-27.
  3. Equinix End User License Agreement (SLED), Equinix, LLC (hosted by Carahsoft), 2023. Section 8, Removal of Customer’s Equipment. One published contract; your own agreement governs. Checked 2026-11-27.
  4. Data Center Decommissioning Guide: Scope, costs and project planning, ITAMG. ITAD provider. Cited for its scope, cost-driver, pricing-structure and custody guidance. Checked 2026-11-27.
  5. Data Center Decommissioning & Recycling Services (hyperscale customer story), Iron Mountain. Company-reported case figures, not independently verified. Checked 2026-11-27.
  6. Data Center Decommissioning Cost Guide: What Phoenix Businesses Should Expect in 2026, Phoenix ITAD, Updated June 2026. Estimated ranges the company says come from its own project history in Phoenix, Arizona. Checked 2026-11-27.
  7. Your Guide to the Data Center Decommissioning Process, Park Place Technologies (Mike Nicholis), March 28, 2022. Checked 2026-11-27.
  8. Data Center Decommissioning Process and Server Recycling Checklist, Modern Waste Solutions. Go/no-go criteria and client/vendor responsibility split. Checked 2026-11-27.
  9. Data Center Decommissioning Services, DC Decom. Describes lease restoration, cable abatement and removal of power and cooling systems as services it offers. Checked 2026-11-27.
  10. Server Decommissioning Workshop, Uptime Institute. Checked 2026-11-27.
  11. Guidelines for Media Sanitization: NIST Publishes SP 800-88r2, NIST Computer Security Resource Center, September 26, 2025. Summary of what changed from Revision 1 (2014). Checked 2026-11-27.
  12. Media sanitization guidelines, Internal Revenue Service. Rules for federal tax information (FTI) held by agencies. Checked 2026-11-27.
  13. Universal Waste, U.S. Environmental Protection Agency, Last updated September 18, 2026. Federal rules at 40 CFR part 273. Checked 2026-11-27.
  14. Lithium-Ion Battery Recycling Frequently Asked Questions, U.S. Environmental Protection Agency, Last updated July 30, 2026. FAQs from EPA’s May 24, 2023 memo on the regulatory status of lithium batteries. Checked 2026-11-27.
  15. Stationary Refrigeration Safe Disposal Requirements, U.S. Environmental Protection Agency, Last updated March 23, 2026. Clean Air Act Section 608; 40 CFR part 82, subpart F. Checked 2026-11-27.
  16. Section 608 Technician Certification Requirements, U.S. Environmental Protection Agency, Last updated November 16, 2026. Checked 2026-11-27.
  17. Guidance for the EPA Halon Emission Reduction Rule (40 CFR Part 82, Subpart H), U.S. Environmental Protection Agency. Explains the disposal provisions at 40 CFR 82.270(d) and (e). Checked 2026-11-27.
  18. 29 CFR 1910.333, Selection and use of work practices, Electronic Code of Federal Regulations (eCFR), OSHA. Checked 2026-11-27.
  19. Removal or Tagging of Abandoned Cables, ElectricalLicenseRenewal.com. Continuing-education page quoting NFPA 70 (NEC) sections 725.25 and 800.25. Section numbers vary by edition; your jurisdiction’s adopted edition governs. Checked 2026-11-27.