What data center decommissioning includes
A decommissioning project has three layers, and quotes often cover only the first: the IT equipment, the workloads and data on it, and the facility around it. ITAMG, an ITAD provider, splits the work the same way: workload migration, IT equipment decommissioning, and facility decommissioning, which it says should be specified separately from the IT work.4 A partial job, such as retiring a row of servers in a live room, uses the same steps at smaller scale; Uptime Institute says underutilized and comatose servers typically make up 20 to 30% of a company's server install base, so discovery alone often finds hardware nobody needs.10
| Workstream | What it covers | Usually done by |
|---|---|---|
| Inventory and asset audit | Every rack, device, drive, cable, UPS and battery string, with serial numbers, owner, location and the planned outcome for each.47 | Your IT team, often with the provider's discovery tools |
| Migration and dependencies | Moving or archiving each workload, then signed acceptance before anything is switched off.84 | IT and application owners |
| Change freeze and power-down | Approved shutdown windows, ordered shutdown of software and hardware, then electrical isolation by qualified people.7818 | IT, facilities, electricians |
| De-racking and de-cabling | Removing servers, storage, network gear, rails, PDUs and IT cabling from racks.57 | Decommissioning or ITAD provider |
| Data sanitization | Erasure or destruction of every drive and data-bearing device, on site or at the provider's plant, with device-level records.4 | Provider, to the method you approve |
| Packing and logistics | Protective packing, sealed containers, manifests, transport and a receiving count that matches what left.4 | Provider |
| Resale, redeployment and recycling | Routing each asset to reuse, resale, return to its lessor or certified recycling, with a settlement report.47 | Provider; you approve routes |
| Infrastructure removal | UPS systems and batteries, CRAC/CRAH units, raised floor, cable trays and abandoned cable, as your lease or plans require.49 | Provider and licensed trades |
| Lease restoration and handback | Returning the space to the condition the lease or colocation contract requires, then a walk-through and sign-off.91 | You, landlord or colocation provider |
| Final reporting | Asset reconciliation, sanitization and destruction certificates, recycling records, and updates to finance for write-offs and cancelled maintenance contracts.74 | Provider delivers; you reconcile |
Decommissioning is not the same as relocation. Relocation moves equipment to a new site and keeps it running; decommissioning shuts the old site down, and most exits do some of each.1 For a general explanation of IT asset disposition, see the ITAD services overview.
The phases of a decommissioning project, in order
Run the project in seven phases, each closed by a sign-off before the next starts. The order matters most at two gates: nothing is powered down until the workload owner signs a go/no-go, and nothing leaves the building until it is on the approved asset list.84
- Discover. Build the baseline inventory and dependency map: applications, databases, storage, backups, network routes, authentication, monitoring and external connections. Record leased and third-party-owned equipment, and every contract with a notice date.871
- Select a provider. Issue the RFP with the inventory attached, hold a site walk so bidders see access, loading docks and floor limits, and award with a written scope and change process.48
- Migrate. Move workloads in waves with both sites live until each wave is accepted; verify backups and test restores first.18
- Power down. Freeze changes, shut down in an agreed order, then have qualified electrical staff isolate and lock out circuits. IT shutdown and electrical de-energization are different steps with different owners.818
- Remove. Sanitize or destroy media, de-rack, pack, seal and ship, recording each custody handover. Reconcile what was approved, what was removed and what was received.4
- Restore. Remove infrastructure the lease or your plans require, from cabling to UPS and cooling units, using licensed trades for electrical and refrigerant work.49
- Close out. Walk the space with the landlord or colocation provider, return badges and keys, file certificates, and give finance the write-offs, resale proceeds and cancelled support contracts.71
Data center decommissioning checklist
Use this as a working checklist; each line should end up with an owner, a date and evidence. It prints cleanly from your browser. It's compiled from the process guides and federal rules cited on this page.8471
Before you start
- Name one accountable project owner and define the scope: which rooms, cages, racks, circuits and contracts are in, and which are out.8
- List every notice date: lease, colocation contract, carrier circuits, maintenance and software support.17
- Confirm in writing what the lease or colocation contract requires you to remove or restore, and who owns racks, PDUs, UPS, cooling and raised floor.43
- Set the budget with service costs and expected resale credit as separate lines.4
Inventory and asset audit
- Scan every device by serial number and asset tag; reconcile against your asset management records.74
- List every data-bearing item separately: drives in servers and arrays, loose drives, SSDs, backup tapes and storage embedded in network or management gear.4
- Flag leased and third-party equipment, with the lessor's return and data-handling instructions.4
- Assign each asset an outcome: redeploy, resell, return, destroy or recycle.4
- Inventory UPS battery strings (chemistry, count, condition), cooling units holding refrigerant, and any halon fire suppression.8141517
Migration and go/no-go
- Map dependencies, including DNS, firewall rules, authentication, certificates, monitoring and remote management.8
- Verify backups and test restores for systems being retired or moved.8
- Get workload owners' written acceptance for each migration wave.8
- Hold a formal go/no-go with named authority to stop, and let technicians stop work if they find live links or unknown drives.8
Power-down and de-installation
- Approve the change freeze and shutdown sequence.87
- Have qualified electrical staff de-energize and lock out or tag the circuits before anyone works on or near them.18
- Release each rack for removal only against the approved asset list; keep retained equipment marked.4
- Segregate batteries and keep damaged lithium batteries apart from intact ones.814
Data sanitization and logistics
- Approve the sanitization method and location (on site or off site) for each media type, plus how failed or unreadable drives are handled.4
- Record device-level results and resolve every exception before final payment.4
- Seal containers, list contents on manifests, and record releasing and receiving parties at every handover.4
- Match the receiving count at the provider's facility to what left your site.4
Infrastructure, restoration and handback
- Have refrigerant recovered by EPA-certified technicians before cooling equipment is dismantled or scrapped.1516
- Send halon-containing equipment only to a facility that recovers halon to NFPA 10 and 12A.17
- Route UPS batteries through universal waste (or, for lead-acid, 40 CFR 266 subpart G) and the required DOT packaging.1314
- Remove the accessible portion of abandoned cable, or tag cable you're keeping for future use.19
- Complete restoration, the final walk-through and sign-off, and return keys, badges and access cards.91
Closeout
- Get the final asset reconciliation: approved, removed, received and final outcome, with an exception list.84
- File certificates of sanitization or destruction and recycling records for audit.14
- Update the asset register; give finance resale proceeds and write-offs; cancel maintenance contracts and licenses.71
- Cancel circuits and cross-connects, and confirm the date billing stops.12
Who does what: your team, the provider, facilities, the colo and trades
You own the decisions; the provider does the physical IT work; facilities, the landlord or colocation provider and licensed trades handle the building. Write that split into the statement of work, because disputes usually start where it's vague.84
| Task | Owner | Supports |
|---|---|---|
| Scope, asset list, disposition instructions | Your IT team | Provider scans, reconciles and reports differences8 |
| Migration, go/no-go, shutdown approval | IT and application owners | Provider follows the authorized scope8 |
| Electrical isolation (PDUs, panels, UPS) | Facilities with qualified electrical staff | Provider verifies the boundary before handling818 |
| De-rack, de-cable, pack, transport | Decommissioning or ITAD provider | You approve routes, access and work hours84 |
| Data sanitization or destruction | Provider | You approve the method and any witnessing84 |
| Resale, recycling, settlement | Provider | You approve outcomes and check deductions4 |
| UPS batteries | Provider or battery contractor with a universal waste route | You supply system history and condition813 |
| Refrigerant recovery from cooling units | EPA Section 608 certified technician | HVAC contractor or provider subcontract16 |
| Halon or other fire suppression | Fire protection contractor | Recovery facility operating to NFPA 10 and 12A17 |
| Heavy equipment moves | Riggers | Facilities confirms floor loading, routes and docks8 |
| Raised floor, trays, abandoned cable, restoration | Provider, cable abatement or general contractor | Landlord or colo accepts the space94 |
| Notices, cross-connects, final walk | You | Colocation provider or landlord21 |
| Asset register, write-offs, contract cancellations | IT asset management and finance | Provider's final reports7 |
How long decommissioning takes, and a planner
Most of a decommissioning timeline is migration and lead time, not hardware removal. Metro Colo Advisory, a colocation advisor, suggests 9 to 12 months from first inventory to handback for a typical enterprise data center, with the physical shutdown often only the last month or two.1 Removal itself can be fast with enough crews: Iron Mountain reports a hyperscale project of 297 racks and 121,893 drives where all racks were data-free four days after the start and all assets were off site within 14 days.5 What usually sets your dates:
- Notice windows. Equinix asks for a termination date 90 to 365 days after the request; Metro Colo Advisory says retail colocation non-renewal windows of 60 to 90 days are common and 6 to 12 months is common at wholesale.21
- Migration. The number of applications, their dependencies and how many waves the business will accept.81
- Access. Escorts, restricted work windows, loading dock and elevator bookings and floor limits slow crews down.48
- Data treatment. On-site sanitization or shredding needs space, power, setup and throughput; off-site needs secure staging and transport.4
- Infrastructure and restoration. Electrical, refrigerant and structural work need their own specialists and permissions.4
Enter your rack count, exit date and scope. The planner lays out a backward schedule and tells you when discovery must start. Worked example (the defaults): 20 racks in an owned or leased room, a 16-week migration, on-site drive treatment, racks and cable removed, a 4-week buffer and a 90-day notice period need about 32 weeks. Discovery starts 32 weeks before exit, power-down is 12 weeks before, de-installation runs from 11 to 8 weeks before, and notice goes out about 13 weeks before.
Decommissioning timeline planner
PlannerPlan length
32 weeks
Start discovery by
32 weeks before exit
Send notice by
About 13 weeks before exit
Enter your exit date to see calendar dates and whether you have enough time.
| Phase | Weeks before exit | Dates | Led by |
|---|---|---|---|
| Discovery: inventory, serial numbers, dependency map, contracts | 32 weeks before to 28 weeks before | – | Your IT team (provider can help) |
| Provider selection: RFP, site walk, award | 28 weeks before to 22 weeks before | – | IT, procurement, security |
| Migration in waves, then go/no-go sign-off | 28 weeks before to 12 weeks before | – | IT and application owners |
| Change freeze, power-down, electrical isolation | 12 weeks before to 11 weeks before | – | IT, facilities, qualified electricians |
| De-install, on-site sanitization or destruction, pack, remove under custody | 11 weeks before to 8 weeks before | – | Decommissioning/ITAD provider |
| Racks, cable trays and abandoned cable removal | 8 weeks before to 6 weeks before | – | Provider and licensed trades |
| Buffer for slips and punch-list items | 6 weeks before to 2 weeks before | – | Project manager |
| Restoration sign-off and handback to landlord or facilities | 2 weeks before to exit date | – | You, facilities, landlord |
| Final reconciliation, certificates, settlement report | 8 weeks before to 6 weeks before | – | Provider delivers; you reconcile |
How it works: the planner counts backward from your exit date. Durations are our editorial planning assumptions, not industry standards, and are meant to be replaced by your provider's schedule once you have one: discovery 3 weeks plus 1 week per 25 racks; provider selection 6 weeks, run in parallel with migration, with at least 4 weeks between award and power-down for the site survey and crew booking; your migration window; 1 week for change freeze, power-down and electrical isolation; de-install, packing and removal 1 week plus 1 week per 40 racks, plus 1 week when drives are treated on site; infrastructure removal 1 week plus 1 per 50 racks (racks, trays and cable only) or 3 weeks plus 1 per 25 racks (full removal); your buffer; and handback 2 weeks (own or leased facility) or 1 week (colocation). Partial weeks round up. Final reports are assumed 2 weeks after removal for on-site treatment and 4 weeks for off-site, and can land after the exit date. It doesn't account for permits, utility work, holidays or restricted work windows.
What decommissioning costs, and how resale offsets it
Price a decommissioning project as a net figure: the service cost minus the resale credit you actually receive. ITAMG puts it as net project cost equals agreed service and project costs minus net recovery credited to you, and notes that a negative result is estimated proceeds, not a promised payout.4 There is no published industry price index; the only per-project ranges we found come from individual providers.
| Cost driver | Why it moves the price | What to clarify |
|---|---|---|
| Labor and access | Dense racks, heavy equipment, escorts and restricted windows add labor. | Shifts, mobilization, minimum charges, waiting time, extra visits |
| Data treatment | Media type, volume, method and location change throughput. | Per-device charges, on-site setup, witnessing, failed-media handling |
| Packing and transport | Destination, protection and site constraints drive logistics. | Packaging, crating, freight, insurance, storage |
| Facility work | Cable removal, specialist disconnections and restoration go beyond collection. | Exact handback condition, contractor boundaries, permits, disposal streams |
| Processing and reporting | Testing, sorting, reconciliation and evidence take work after pickup. | Included reports, delivery dates, recycling charges |
| Recovery credit | Model, configuration, condition, ownership and demand set resale value. | Firm offer or estimate; deductions, settlement timing, unsold items |
Source: ITAMG.4
One provider publishes ranges. Treat them as that company's estimates for its own market, not a quote or a national benchmark:
| Project size | Asset count | Estimated cost | Value recovery potential |
|---|---|---|---|
| Small server room | 1 to 10 racks, under 100 assets | $2,500 to $8,000 | $3,000 to $15,000 |
| Mid-size data center | 10 to 50 racks, 100 to 500 assets | $8,000 to $35,000 | $15,000 to $75,000 |
| Large enterprise data center | 50 to 200 racks, 500 to 2,000 assets | $35,000 to $150,000 | $50,000 to $300,000 |
| Hyperscale or multi-site | 200+ racks, 2,000+ assets | Custom pricing | $200,000+ |
Source: Phoenix ITAD, updated June 2026.6 The company says actual costs depend on project requirements. Recovery depends heavily on equipment age and configuration; older or end-of-support hardware may recover little.
At the large end, Iron Mountain reports $4.4 million in client proceeds from remarketing the equipment in its 297-rack hyperscale case.5 Three cautions apply to any offset:
- Know what kind of credit you're getting. A firm purchase offer, a forecast and a share of future sale proceeds commit the provider to very different things. Ask about deductions, payment timing and who bears unsold equipment.4
- Don't destroy value by default. Get a resale assessment before approving treatment that removes the resale option, such as shredding drives in equipment that could be resold after verified erasure.4
- Infrastructure work is usually extra. Restoration, cable abatement and UPS or cooling removal are often quoted separately from the IT scope.49
The biggest exit costs often sit outside the decommissioning quote: overlapping rent while both sites run, migration labor and the new environment.1 For how buyback offers for servers, storage and network gear are built, see server recycling and buyback.
Data sanitization during decommissioning: on site or off site
Decide the method and the location for each media type before any device is released, and get device-level records back. Treat on site when your policy says media can't leave unsanitized or you need witnessing; treat off site when policy allows controlled transport, with custody controls for unsanitized media in transit.4
- Use the current NIST guidance. NIST published SP 800-88 Revision 2 on September 26, 2025. It shifts the focus to running an enterprise media sanitization program and, apart from cryptographic erase, replaces technique details with a recommendation to follow IEEE 2883, NSA specifications or an organizationally approved standard.11
- Find all the media. Formatting a volume or deleting a virtual machine doesn't sanitize the drive under it; include loose drives, tapes and storage embedded in network and management equipment.4
- Check agency-specific rules. For example, the IRS requires that destruction of media holding federal tax information be witnessed by an agency employee, with limited exemptions written into the contract.12
Choosing between erasure, purge and destruction, and what a valid certificate must show, is covered in certified data destruction and NIST 800-88 methods. For shred trucks, particle sizes and per-drive pricing, see hard drive shredding services.
Batteries, refrigerants, halon and electrical safety
Facility equipment brings federal environmental and safety rules that IT equipment doesn't, and states can be stricter. Confirm the provider or its named subcontractor handles each one.14
| Item | Federal rule (summary) | What to require |
|---|---|---|
| Lithium-ion UPS batteries | EPA says most lithium batteries are likely hazardous waste at disposal (ignitable and reactive) and recommends businesses manage them under the universal waste rules, 40 CFR part 273. Damaged batteries can't go by air and need DOT packaging under 49 CFR 173.185(f).14 | A named recycler, segregation of damaged units, trained handlers, DOT-compliant packing |
| Lead-acid (VRLA or flooded) UPS batteries | Spent lead-acid batteries can be managed under 40 CFR part 266, subpart G, or under the universal waste rules.13 | Which rule the provider uses, the destination recycler, shipping records |
| Universal waste limits | Small quantity handlers accumulate under 5,000 kg; large quantity handlers 5,000 kg or more. Universal waste can generally be stored for a year and shipped without a hazardous waste manifest.13 | Weigh the battery plant against the 5,000 kg threshold; set a removal date |
| Refrigerant in cooling equipment | Equipment typically dismantled on site, such as chillers, must have refrigerant recovered under EPA's servicing rules before disposal. Technicians who dispose of equipment that could release refrigerant must be Section 608 certified.1516 | The technician's certification type, recovery records, where the refrigerant goes |
| Halon fire suppression | Halon-containing equipment may be disposed of only by sending it for halon recovery to a facility operating to NFPA 10 and 12A; halon itself only goes to recycling or approved destruction.17 | The fire protection contractor and recovery facility |
| Electrical work | OSHA requires live parts be de-energized before employees work on or near them (with narrow exceptions) and the circuits locked out, tagged or both.18 | A site safety plan naming who isolates and verifies each circuit |
| Abandoned cable | The NEC requires removal of the accessible portion of abandoned communications and Class 2/3 cable unless it's tagged for future use.19 | A cable scope that matches your code edition and your lease |
State e-waste laws, landfill bans and downstream recycler certification are covered in the IT equipment recycling guide.
The risks that cause most decommissioning problems
Most failures are record-keeping failures, not equipment failures: a missed dependency, a drive nobody listed, a serial number that doesn't reconcile, or a contract that renewed because notice went out late.814
| Risk | What it looks like | Control |
|---|---|---|
| Live dependency switched off | Production traffic, a shared key or an authentication service still on old hardware.8 | Dependency map, traffic validation and a signed go/no-go |
| Missed or extra assets | Devices on the floor that aren't on the list, or the reverse.74 | Serial-level baseline; removal only against the approved list |
| Lost serials in transit | A shipment arrives but a device can't be matched. GPS shows where a truck went, not whether a device arrived.4 | Sealed containers, manifests, receiving reconciliation |
| Data exposure | Loose drives, tapes or embedded storage outside the sanitization scope; failed drives with no exception route.4 | Separate media inventory; device-level results; resolved exceptions |
| Selling what you don't own | Leased or third-party equipment sent for resale.4 | Ownership flagged in the inventory; lessor instructions followed |
| Contract renews or charges continue | A missed non-renewal window, or circuits and support contracts left running.17 | Notice calendar; cancellation list with dates billing stops |
| Battery fire or release | Damaged lithium cells mixed with intact ones or stored near combustibles.14 | Segregation, inspections, trained handlers, EPA storage practices |
| Refrigerant or halon vented | Cooling or suppression equipment scrapped without recovery.1517 | Certified technicians; recovery records before removal |
| Electrical injury | IT shutdown mistaken for electrical isolation.818 | Lockout/tagout by qualified staff; verified boundaries |
Leaving a colocation cage: what's different
In colocation, the contract sets the clock: you give notice, remove everything by the end date and leave the space as the contract requires. The building, power and cooling usually stay with the provider, so infrastructure removal is rarely yours, but cabinets, cabling and cage contents may be.14
- Notice. Equinix's process asks for a preferred termination date 90 to 365 days after the request; billing ends on the termination date, and for full account or deployment terminations a customer project manager assists with decommissioning.2 Retail and wholesale windows vary; Metro Colo Advisory says a missed window can renew the contract for another full term.1
- Removal deadline. In one published Equinix agreement, the customer must remove all equipment on or before expiry. After 10 days Equinix may remove and return it at the customer's risk and invoice the cost, may treat unclaimed equipment as abandoned, and after 30 days' written notice may liquidate it and keep the proceeds.3 Equipment that leaves your control that way could still hold drives, so finish sanitization well before the deadline.
- Circuits and cross-connects. Cancel carrier circuits and interconnections separately and confirm the date each stops billing.14
- Site rules. Book loading docks, escorts and work windows with the colocation provider, and get its handback requirements in writing before you scope the job.48
How to choose a data center decommissioning provider
Choose on proof of process for your kind of site: serial-level reconciliation, a sanitization method you've approved, a named route for every regulated item and a clear commercial model. Certifications matter, but check them in the certifier's own registry and confirm which facility and activities they cover.4 For an unranked list of national providers and how to verify their certifications, see the ITAD companies directory.
RFP checklist for decommissioning services
- Scope by workstream. IT de-install, data treatment, logistics, resale and recycling, infrastructure removal and restoration priced as separate lines, with exclusions listed.4
- Certifications. Which R2v3, e-Stewards or NAID AAA certificates apply, to which facilities, and the registry link for each.
- Sanitization. Method by media type and the standard it follows (NIST SP 800-88 Rev. 2, IEEE 2883), on-site capacity and daily throughput, and how failed drives are handled.114
- Chain of custody. Seals, manifests, custody signatures and a sample reconciliation report showing approved, removed, received and final outcome.48
- Commercial model. Fixed price, time and materials, or recovery share; for any credit, whether it's a firm offer, the deductions, settlement timing and unsold-equipment terms.4
- Regulated items. Battery recycler and handling rule, refrigerant technicians' Section 608 certification, halon recovery facility.131617
- Safety. A site-specific safety plan, who performs electrical isolation, and how lockout boundaries are verified.188
- Subcontractors. Every subcontractor named, with the work each does.
- Insurance. Certificates for the coverage types and limits your risk team requires.
- Schedule. Crew size, shifts, mobilization date and the date each report is delivered.4
- Downstream. Where equipment and materials go after the provider's plant, and how that is documented.4
- References. Two recent projects of similar size and type (owned room, colocation exit or full facility).
Limits of this guide
This page summarizes published sources as they read on November 27, 2026. It isn't legal, environmental or engineering advice. Federal rules are summarized; states can be stricter, and the NEC edition in force depends on your jurisdiction. Contract terms quoted come from one provider's published documents; your own lease or colocation agreement governs. Cost figures are one vendor's estimates for one market and aren't a quote. The planner's durations are our editorial assumptions, not industry standards. We haven't verified any company's claims, and citing a company isn't an endorsement.
What to send for a decommissioning quote
A provider can scope the job and plan a site walk faster with these details:
- Site address, and whether it's your own facility, a leased building or a colocation cage.
- Rack count, rough device counts by type, and the number of drives if known.
- Exit date and any notice date already set.
- Where drives must be treated (on site or off site), and any witnessing or regulatory requirement.
- Infrastructure in scope: none, racks and cabling, or UPS, batteries, cooling and raised floor too.
- Leased or third-party equipment, and what you hope to resell or redeploy.
- Access limits: work hours, escorts, loading dock, elevator and floor-loading constraints.
The planner's "Add this schedule to my quote request" button copies your inputs and dates into the form.
Request decommissioning quotes through IT Asset Disposal Services
Send one request with your project details. A person reviews it and, where we can identify providers that fit the site and scope, shares it with up to two of them. We don't yet have agreements with any providers, so we can't promise how many will respond or how quickly. Any provider that does contacts you directly, and you decide whether to hire anyone. It's free for buyers. Providers who receive requests may pay us a referral commission; the referral disclosure explains how. We don't de-install, sanitize, transport, recycle or buy equipment, and routing a request isn't an endorsement. Read how requests are handled, or go to the request form.
Request decommissioning quotes
Sources
- Data Center Decommissioning: The Process, Checklist and Timeline, Metro Colo Advisory, Updated November 22, 2026. Colocation advisory firm that says providers pay it for placements. Cited for its planning-lead and notice-window guidance, which it describes as typical terms. Checked 2026-11-27.
- Termination Requests, Equinix Product Documentation. How Equinix customers request a full account, deployment or product termination. Checked 2026-11-27.
- Equinix End User License Agreement (SLED), Equinix, LLC (hosted by Carahsoft), 2023. Section 8, Removal of Customer’s Equipment. One published contract; your own agreement governs. Checked 2026-11-27.
- Data Center Decommissioning Guide: Scope, costs and project planning, ITAMG. ITAD provider. Cited for its scope, cost-driver, pricing-structure and custody guidance. Checked 2026-11-27.
- Data Center Decommissioning & Recycling Services (hyperscale customer story), Iron Mountain. Company-reported case figures, not independently verified. Checked 2026-11-27.
- Data Center Decommissioning Cost Guide: What Phoenix Businesses Should Expect in 2026, Phoenix ITAD, Updated June 2026. Estimated ranges the company says come from its own project history in Phoenix, Arizona. Checked 2026-11-27.
- Your Guide to the Data Center Decommissioning Process, Park Place Technologies (Mike Nicholis), March 28, 2022. Checked 2026-11-27.
- Data Center Decommissioning Process and Server Recycling Checklist, Modern Waste Solutions. Go/no-go criteria and client/vendor responsibility split. Checked 2026-11-27.
- Data Center Decommissioning Services, DC Decom. Describes lease restoration, cable abatement and removal of power and cooling systems as services it offers. Checked 2026-11-27.
- Server Decommissioning Workshop, Uptime Institute. Checked 2026-11-27.
- Guidelines for Media Sanitization: NIST Publishes SP 800-88r2, NIST Computer Security Resource Center, September 26, 2025. Summary of what changed from Revision 1 (2014). Checked 2026-11-27.
- Media sanitization guidelines, Internal Revenue Service. Rules for federal tax information (FTI) held by agencies. Checked 2026-11-27.
- Universal Waste, U.S. Environmental Protection Agency, Last updated September 18, 2026. Federal rules at 40 CFR part 273. Checked 2026-11-27.
- Lithium-Ion Battery Recycling Frequently Asked Questions, U.S. Environmental Protection Agency, Last updated July 30, 2026. FAQs from EPA’s May 24, 2023 memo on the regulatory status of lithium batteries. Checked 2026-11-27.
- Stationary Refrigeration Safe Disposal Requirements, U.S. Environmental Protection Agency, Last updated March 23, 2026. Clean Air Act Section 608; 40 CFR part 82, subpart F. Checked 2026-11-27.
- Section 608 Technician Certification Requirements, U.S. Environmental Protection Agency, Last updated November 16, 2026. Checked 2026-11-27.
- Guidance for the EPA Halon Emission Reduction Rule (40 CFR Part 82, Subpart H), U.S. Environmental Protection Agency. Explains the disposal provisions at 40 CFR 82.270(d) and (e). Checked 2026-11-27.
- 29 CFR 1910.333, Selection and use of work practices, Electronic Code of Federal Regulations (eCFR), OSHA. Checked 2026-11-27.
- Removal or Tagging of Abandoned Cables, ElectricalLicenseRenewal.com. Continuing-education page quoting NFPA 70 (NEC) sections 725.25 and 800.25. Section numbers vary by edition; your jurisdiction’s adopted edition governs. Checked 2026-11-27.